PHOSPHORIC ACID & DAP FERTILIZER PLANT PROJECTS - ETİ BAKIR

Project Name

01

Location

SAMSUN, TURKIYE

03

Date

2022

05

Duration

15 MONTHS

04

Service

ENGINEERING, FABRICATION, PROCUREMENT, ERECTION, COMMISSIONING

DEHA TECH PLAYED A KEY ROLE IN THE DEVELOPMENT OF ETI BAKIR’S INTEGRATED FERTILIZER PRODUCTION COMPLEX BY DELIVERING CRITICAL MECHANICAL WORKS FROM RAW MATERIAL HANDLING TO FINISHED PRODUCT PROCESSING.

THE SCOPE INCLUDED GRINDING MILL INSTALLATION AND COMMISSIONING, STEEL STRUCTURES, PORT AND PROCESS CONVEYOR SYSTEMS, PROCESS EQUIPMENT, CYCLONES, INTERCONNECTING SYSTEMS, AND COMMISSIONING ACTIVITIES.

DEHA TECH ALSO EXECUTED THE INTEGRATION WORKS BETWEEN THE SULFURIC ACID PLANT AND THE PHOSPHORIC ACID PLANT, CONTRIBUTING TO THE SUCCESSFUL OPERATION OF THE COMPLETE PHOSPHORIC ACID AND DAP FERTILIZER PRODUCTION CHAIN.