BAGFAS AMMONIUM NITRATE / CALCIUM AMMONIUM NITRATE PLANT
Project Name
Location
TURKEY
Date
2015
Service
ERECTION
Duration
8 MONTHS
Scope
450 TON STEEL STRUCTURE BUILDING ERECTION,
250 TON PROCESS DUCT & CHUTE SITE ERECTION,
15,000 WDI CS & SS SPOOL PIPING INSTALLATION,
12,000 M² BUILDING ROOF AND FACADE CLADDING INSTALLATION.
![7 7](https://dehatech.com/wp-content/uploads/2020/11/7-1-600x730.jpg)
![1](https://dehatech.com/wp-content/uploads/2020/11/1-3.jpg)
![Bagfas Fertilizer Plant (1948) Bagfas Fertilizer Plant (1948)](https://dehatech.com/wp-content/uploads/2020/11/Bagfas-Fertilizer-Plant-1948-rotated-650x550.jpg)
![Bagfas Fertilizer Plant (1067) Bagfas Fertilizer Plant (1067)](https://dehatech.com/wp-content/uploads/2020/11/Bagfas-Fertilizer-Plant-1067-scaled-750x570.jpg)
![Bagfas Fertilizer Plant (1464) Bagfas Fertilizer Plant (1464)](https://dehatech.com/wp-content/uploads/2020/11/Bagfas-Fertilizer-Plant-1464-650x550.jpg)
![Bagfas Fertilizer Plant (35)](https://dehatech.com/wp-content/uploads/2020/11/Bagfas-Fertilizer-Plant-35-scaled.jpg)
![2 2](https://dehatech.com/wp-content/uploads/2020/11/2-4.jpg)
![4](https://dehatech.com/wp-content/uploads/2020/11/4-4.jpg)
![3 3](https://dehatech.com/wp-content/uploads/2020/11/3-4.jpg)
![Bagfas Fertilizer Plant (523)](https://dehatech.com/wp-content/uploads/2020/11/Bagfas-Fertilizer-Plant-523-scaled.jpg)
![Bagfas Fertilizer Plant (243)](https://dehatech.com/wp-content/uploads/2020/11/Bagfas-Fertilizer-Plant-243-scaled.jpg)