AMMONIUM NITRATE / CALCIUM AMMONIUM NITRATE PLANT PROJECT FOR BAGFAS

Project Name

01

Location

BANDIRMA, BALIKESİR, TURKİYE

03

Date

2018

05

Duration

18 MONTHS

02

Status

COMPLETED

04

Service

MANUFACTURING AND ERECTION

06

Scope

6450 TON STEEL STRUCTURE BUILDING AND PROCESS EQUIPMENT ERECTION,

850 TON PROCESS DUCT & CHUTE SITE ERECTION,

SITE ERECTED CRYOGENIC TANKS ERECTION

135,000 WDI CS & SS SPOOL PIPING MANUFACTURING AND INSTALLATION,

17,000 M² BUILDING ROOF AND FACADE CLADDING INSTALLATION

7
Bagfas Fertilizer Plant (1464)
3
Bagfas Fertilizer Plant (1948)
2
Bagfas Fertilizer Plant (1067)